This timeline started one week prior to 23rd May , The greened elements are completed ( in SVN )

Phase I (1 weeks)

Finalize the project specifications

Phase II (2 weeks)

  • Backend workflow list view
  • Backend workflow creation view
  • Core plugin
  • “com_content” component handler

Phase III (2 weeks)

  • “Comments” custom field
  • “File attachment” custom field
  • Frontend task view
  • Backend task view

Phase IV (2 weeks)

  • ACL handling for “com_content”
  • Debugging/Testing

Any remaining time before GSoC 2009 end will be used for debugging and stabilization